BICSI Registered Communications Distribution Designer Version 14 is available, candidates are required to pass the RCDDv14 exam successfully to earn this certification. When deciding to prepare for the BICSI RCDDv14 exam by using the online resource, we suggest you choose the new BICSI RCDDv14 exam questions from ITExamShop. By having the new BICSI RCDDv14 exam questions of ITExamShop, you can simply pass the BICSI Registered Communications Distribution Designer – RCDDv14 exam with 100% passing guarantee.

Having the BICSI Registered Communications Distribution Designer – RCDDv14 free demo questions first:

Page 1 of 4

1. Using a vertical cable support structure can create issues for the cable attached to the pathway Several issues can result It the support work is not clone correctly.

Which two of the following conditions could be caused by a poorly supported cabled (Select two options.)

2. When preparing an upfront cost estimate, the ICT distribution designer MUST consider which two of the following fees? (Select two options.)

3. The transfer of unwanted signals may occur over one path or several paths.

What method addresses the mitigation or suppression of unwanted signals?

4. Before working on equipment, what is the FINAL step in the lockout/tagout (LOTO) procedure?

5. Which two of the following roles do an ICT distribution designer use to ensure a timely and cost-effective telecommunications construction project? (Select two options.)

6. When estimating an ICT distribution designer project timeline schedule based on the scope of work which two scheduling methods use network diagrams lo integrate logical activities and identify critical paths on the project? (Select two options.)

7. Which of the following is a common application for exothermic welding of earthing (grounding) and bonding conductors?

8. During bidding the ICT distribution designer should review the bid responses for compliance and completeness. Afterwards, the designer should report the findings and recommendations to the

9. The size and number of conduits or sleeves used for backbone pathways depend on the usable floor space served by the backbone distribution system.

What is the MINIMUM trade size of sleeves recommended to serve a TR, ER, or EF?

10. What is the OPTIMAL lime in the construction process for ICT submittals to be reviewed by the ICT distribution designer?